Category: 1. Project News

  • Complex manoeuvres to install the Cold Powering System into the IT String

    Complex manoeuvres to install the Cold Powering System into the IT String

    An impressive operation took place in CERN’s magnet test hall, SM18. The High Temperature Superconductor (HTS) based Cold Powering System has been installed into the Inner Triplet (IT) String.

    Explore →

  • Amorphous carbon coating in the beam screens for the circulating beam in the cryomodules for the crab cavities: production completed

    Amorphous carbon coating in the beam screens for the circulating beam in the cryomodules for the crab cavities: production completed

    The non-crabbed line in the cryomodules for the HL-LHC crab cavities host a carbon-coated beam screen.

    Explore →

  • Update on the reconfiguration of the test benches at SM18 for the cold tests of the HL-LHC cryo-magnets

    Update on the reconfiguration of the test benches at SM18 for the cold tests of the HL-LHC cryo-magnets

    The qualification tests of the new cryo-magnet assemblies, to ensure their compliance with the HL-LHC specifications, requires a substantial upgrade of the cryogenic test stations in SM18

    Explore →

  • HiRadMat test completed: a crucial step for the HL-LHC beam dump

    HiRadMat test completed: a crucial step for the HL-LHC beam dump

    The 65th HiRadMat experiment (HRMT-HLTDE) was completed by the SY-STI team on the 14th August 2024. This experiment is a crucial step in validating the material selection for the HL-LHC beam dumps (TDEs) in HL work package 14 and is the product of around 12 months of ideation and planning.

    Explore →

  • SQXL commissioning phase 1C successfully completed

    SQXL commissioning phase 1C successfully completed

    The SQXL cryogenic line, an essential component of the HL-LHC IT String, has recently undergone an additional series of commissioning tests in standalone mode without the magnets.

    Explore →

  • Series production validated for the pre-series DQHDS units

    Series production validated for the pre-series DQHDS units

    The four Quench Heater Discharge Power Supply (DQHDS) pre-series units have recently arrived at CERN. These units, produced in Japan, by NICHICON CORPORATION,

    Explore →

  • Large helium tanks delivered for the HL-LHC

    Large helium tanks delivered for the HL-LHC

    Exceptional machines call for exceptional operations. Two large helium tanks for the High-Luminosity LHC (HL-LHC) were installed at Point 1 in June, and two more at Point 5 in July.

    Explore →

  • Fourth consecutive MQXFB magnet to reach the HL-LHC requirements for operation

    Fourth consecutive MQXFB magnet to reach the HL-LHC requirements for operation

    The test of LMQXFB04 (Q2 cold mass containing MQXFB04 and the corrector MCBXFB02b) has been completed, making it the fourth consecutive MQXFB magnet (CERN-produced Nb3Sn triple quadrupole magnet series),

    Explore →

  • HL-LHC Collaboration Board Newsletter #8 – now available

    HL-LHC Collaboration Board Newsletter #8 – now available

    The 8th issue of the annual HL-LHC Collaboration Board Newsletter is now available!

    Explore →

  • HL-LHC IT String advancements and challenges for 2024

    HL-LHC IT String advancements and challenges for 2024

    By WP16 HL-LHC IT STRING team. The commissioning of key equipment on the metallic platform is now completed. Accelerating News #47.

    Explore →